Software Partner Selection

A Software Development RFP That Produces Comparable Proposals

Most RFPs produce proposals that cannot be compared, because every vendor fills the gaps with different assumptions. This guide gives a section-by-section RFP template, a weighted scorecard with a scoring rubric, and a worked example for a quotation and scheduling app.

TopicsSoftware Partner SelectionSoftware Costs and BudgetsDedicated Teams and Outsourcing

Key takeaways

  • An RFP works when it makes proposals comparable, not when it is long. Every gap in the RFP becomes a different assumption in each proposal.
  • Describe outcomes, users, workflows, data, integrations and constraints. Leave the solution design to the vendors unless a choice is already fixed.
  • Ask every vendor for the same artefacts: assumptions, exclusions, team, plan, risks and a price in a fixed format.
  • Score with a weighted scorecard and a written rubric, agreed before proposals arrive, so the decision can be explained later.
  • If the scope is still uncertain, ask for a priced discovery phase rather than a binding quote for the whole build.

A request for proposal (RFP) is meant to help you choose a software development partner. In practice, many RFPs make the choice harder. One vendor quotes a three-month build, another nine months; one includes testing and hosting, another assumes you will provide them. The proposals differ less because the vendors differ than because the RFP left room for interpretation.

This guide is written for the buyer: a founder, CTO, product owner or procurement lead issuing an RFP. It explains what to include, how to keep proposals comparable and how to score them. For the wider question of judging a vendor’s capability, see our guide to evaluating a software outsourcing company.

When an RFP is the right tool

An RFP suits projects where you can describe the problem, the users and the main workflows, and where you want several vendors to compete on approach and price. It is less useful when:

  • The problem is still unclear. Vendors will guess, and their guesses will not be comparable. Run a short discovery phase first.
  • You already know the partner you want. A request for quotation or a direct discovery engagement is faster.
  • You need people, not a project. If you want engineers under your own management, ask for team profiles and rates for a dedicated team rather than a fixed-scope proposal.

The RFP template, section by section

SectionWhat to includeWhy it matters
———
1. BackgroundYour organisation, the business problem, why nowLets vendors judge fit and ask useful questions
2. OutcomesMeasurable goals and how you will judge successAnchors scope trade-offs to value
3. Users and workflowsUser types, main journeys, volumesDrives design, effort and testing
4. ScopeMust-have, should-have and out-of-scope itemsReduces each vendor’s guesswork
5. Data and integrationsSystems to connect, data to migrate, ownershipIntegrations are a common source of overruns
6. ConstraintsBudget range, deadlines, compliance, hosting, technology that is already fixedPrevents proposals you cannot accept
7. Non-functional needsPerformance, availability, security, accessibility, supported devicesHidden cost drivers if left unstated
8. Delivery expectationsEngagement model, governance, reporting, acceptance, warranty and supportShapes team and price
9. Response formatRequired sections, price template, page limitsMakes proposals comparable
10. Process and timelineQuestion deadline, submission date, presentations, decision dateGives vendors time to answer well
11. EvaluationCriteria and weightsEncourages vendors to address what you value

An RFP template for custom software development. Remove sections that do not apply rather than leaving them vague.

Describe outcomes before features

A feature list invites vendors to price the features. A stated outcome lets them propose a simpler way to reach it. Compare:

  • *Feature:* “The app must have a quote builder with 40 configurable fields.”
  • *Outcome:* “Sales staff should produce an accurate quote on site in under ten minutes, instead of the current two days.”

Keep the feature list too, but mark which items are fixed and which are open to alternatives.

Be explicit about what is fixed

If you must use a particular cloud provider, identity provider or framework, say so. If you do not mind, say that as well. Vendors who do not know will either price their preferred stack or hedge with expensive options.

State a budget range

Many buyers hide the budget, hoping for lower bids. The usual result is proposals that range from a minimal build to a gold-plated one, which cannot be compared. A range, even a wide one, lets vendors shape the scope to what you can afford. Our guide to software development costs in Vietnam gives reference rates if you need to set an initial range.

Ask every vendor for the same answer format

The response format is the part of the RFP that makes comparison possible. Require each proposal to contain:

  1. Understanding of the problem in the vendor’s own words, in no more than one page.
  2. Proposed approach and the reasons for it, including alternatives considered.
  3. Assumptions and exclusions, listed explicitly. This section is often the most revealing.
  4. Team with roles, seniority, allocation and who will be named on the project.
  5. Plan with phases, milestones and what is delivered at each.
  6. Risks the vendor sees and how it proposes to manage them.
  7. Price in your template, separated into discovery, build, testing, deployment, warranty and ongoing support.
  8. Evidence: relevant work, references you may contact and samples of documentation or code where possible.

A fixed price template is the single most useful comparison tool. Ask for effort by phase and role, the rate card behind it and the payment schedule. If a vendor cannot fit its pricing into your template, ask why rather than adjusting yours.

A worked example: a quotation and scheduling app

To make this concrete, consider an illustrative company that services commercial air-conditioning units. Its sales staff produce quotes in spreadsheets and its schedulers assign technicians by phone. It wants a web portal for staff and a mobile app for technicians.

RFP sectionExample wording
——
OutcomeQuotes issued on the day of the site visit; technician utilisation visible to managers daily
Users15 sales staff, 4 schedulers, 60 technicians, managers; about 900 jobs per month
Must-haveQuote builder from a price list, job scheduling, technician mobile job sheet with photos and signature
Out of scopePayroll, inventory purchasing, customer self-service portal (phase 2 at the earliest)
IntegrationsAccounting system for invoices; existing customer list in CSV for migration
ConstraintsMust run on company-managed Android phones; launch before the summer peak; budget range stated
Non-functionalJob sheet usable offline; quotes must not be lost on a weak connection; data hosted in-region
Response formatPrice per phase in the attached template; assumptions listed; named team lead

Illustrative RFP extract. Numbers are invented for the example.

From the same RFP, two proposals now become comparable. If one vendor excludes offline support or assumes the accounting integration is a simple file export, you can see it in their assumptions and ask, rather than discovering it after signing.

Score proposals with a weighted scorecard

Agree criteria, weights and the scoring rubric before you open the first proposal. Doing it afterwards invites people to reverse-engineer scores to justify a favourite.

CriterionWeightWhat a high score looks like
———
Understanding of the problem15%Restates goals accurately and asks sharp questions
Approach and architecture20%Clear reasoning, sensible alternatives, risks addressed
Delivery plan and governance15%Realistic phases, clear acceptance, regular demos
Team and capability20%Named, appropriately senior people with relevant experience
Price and commercial terms20%Complete, transparent, assumptions explicit
Evidence and references10%Comparable work, contactable references

Example weights. Adjust them to your priorities, but fix them before scoring.

A rubric each evaluator can apply the same way

ScoreMeaning
——
0Not addressed
1Addressed vaguely; important gaps or contradictions
2Adequate; some assumptions unstated
3Clear and complete; assumptions stated
4Clear, complete and adds insight we had not considered

A five-point rubric keeps scores comparable across evaluators.

Ask each evaluator to score independently, then compare and discuss differences of two points or more. Record the reasons. A weighted score is a structured input to the decision, not the decision itself: use it to shortlist two or three vendors and then test them with presentations, reference calls and, where the stakes justify it, a paid trial task.

Handling the price score

Price deserves care. The cheapest proposal is often cheap because it assumes less. Before scoring price, normalise proposals: add the cost of anything one vendor excluded and another included, such as testing, project management, deployment or warranty. Our article on the hidden costs of choosing the wrong software partner lists the items most often missing.

Running the process

  • Shortlist three to five vendors. More creates evaluation work without improving the choice.
  • Allow two to four weeks for responses on a substantial project, plus a window for written questions.
  • Share all answers with all vendors. If one vendor asks a good question, everyone should benefit from the answer.
  • Hold presentations with the proposed team, not only the sales team. Ask the named lead to walk through a risky part of the plan.
  • Call references and ask what went wrong and how the vendor handled it.
  • Give feedback to unsuccessful vendors. It costs little and improves the responses you receive next time.

Common RFP mistakes

MistakeEffectFix
———
Copying a generic templateIrrelevant sections, missing essentialsUse a template as a checklist, then write for your project
Prescribing the solutionVendors cannot propose better optionsDescribe outcomes; mark only true constraints as fixed
Hiding the budgetProposals of every sizeGive a range
No response formatProposals cannot be comparedRequire sections and a price template
Asking for a fixed price on an unclear scopeHigh contingency or later change requestsAsk for a priced discovery phase first
Scoring after readingBias towards a favouriteFix criteria and rubric in advance

Most RFP problems come from gaps and timing, not from the wrong vendors.

When to ask for discovery instead of a full quote

If you cannot yet write sections 3 to 7 with confidence, a binding quote for the whole build will carry a large contingency or lead to change requests. A better approach is to ask vendors to price a short discovery phase, typically a few weeks, that produces validated requirements, a design prototype, an architecture outline and a firm estimate. You can then choose to continue with the same vendor or take the outputs elsewhere. Our guide to product discovery frameworks explains what that phase should deliver.

Frequently asked questions

How long should a software development RFP be?

Long enough to describe outcomes, users, scope, constraints and the response format clearly. For most projects that is 8 to 20 pages plus attachments. Length without clarity does not help vendors.

Should we include a budget?

Yes, as a range. It lets vendors propose a scope you can afford and makes proposals comparable.

How many vendors should we invite?

Three to five well-chosen vendors usually give enough choice without overwhelming the evaluation team.

Can we ask for a fixed price?

You can when the scope is well defined. If it is not, ask for a fixed price for discovery and an estimate range for the build.

Sources and methodology

Facts in this article were checked against the sources below. Directory data (ratings, review counts, rate bands and team sizes) changes over time and is shown as published on the date accessed. Illustrative examples are labelled as such and are not quotes.

  1. Netguru: Top 7 RFP Best Practices for Winning Proposals — Reviewed as a baseline; written mainly from the vendor’s side, with no template or scoring rubric

Preparing an RFP for a software project?

Share your draft or your requirements. We will tell you which questions vendors will struggle to answer and respond with a proposal that states its assumptions.